Variation record #1
← review queue · next: #7 test →
Flags
- warn No agreed price or rate basis captured. Record the agreed price (or rate basis) before relying on this variation.
- warn Time / EOT impact not captured — confirm programme effect (enter 0 if none).
- warn Two-party acknowledgement not confirmed. Obtain client co-sign or counter-notice.
- info Low parser confidence (50%) on "client_agreed" — verify against the original message.
- info Engineer involvement mentioned — confirm engineer sign-off is obtained and attached.
- warn Residential job ≥ $30k with no variation clause: written notice to owner due by 2026-07-22 (10 working day(s) left), agreed by co-sign or counter-notice.
Client acknowledgment (WhatsApp — a contractual courtesy, not a legal requirement by itself)
Client agreed: pending
Captured evidence
harness · voice · 2026-07-07T09:58:44.269Z · from Dave (site foreman)
Transcript (provided): “Hey it's Dave, we hit solid rock at the north corner footing, gonna need the engineer to look at it before we pour, probably an extra day and need to order more concrete, maybe 2 cube extra”
Parsed by: mock
Trade attribution
- foundations (LBP, 90%)
Suggested RBW items (pulled into a Record of Work when created for this job)
- primary structure / foundations_subfloor: Foundation / subfloor work referenced in site message