Variation record #3
← review queue · next: #7 test →
Flags
- warn No agreed price or rate basis captured. Record the agreed price (or rate basis) before relying on this variation.
- warn Two-party acknowledgement not confirmed. Obtain client co-sign or counter-notice.
- info Low parser confidence (55%) on "time_impact_days" — verify against the original message.
- info Low parser confidence (50%) on "client_agreed" — verify against the original message.
- info Council/inspection referenced — confirm reinspection is booked and any notice to fix is on file.
- warn Residential job ≥ $30k with no variation clause: written notice to owner due by 2026-07-22 (10 working day(s) left), agreed by co-sign or counter-notice.
Client acknowledgment (WhatsApp — a contractual courtesy, not a legal requirement by itself)
Client agreed: pending
Captured evidence
harness · voice · 2026-07-07T09:58:44.272Z · from Dave (site foreman)
Transcript (provided): “Council inspector failed the framing on the west wall, says the bracing's short, need to add two more panels, that's gonna cost us a day and some extra ply”
Parsed by: mock
Trade attribution
- carpentry (LBP, 90%)
Suggested RBW items (pulled into a Record of Work when created for this job)
- primary structure / bracing: Wall bracing work referenced in site message